IEE of the project has been approved by ministry of Energy |
11th August 2010 |
Grid connection agreement |
31th August 2010 |
Power Purchase agreement(PPA) with NEA |
9th Sep 2011 |
Generation license issued by DOED |
20th March 2017 |
Financial Closure |
4th September 2017 |
Transmission Line survey License |
30th October 2019 |
Required Commercial operation Date (RCOD) |
(17th July 2015) |
Approved Required Commercial date (RCOD) |
(21th Oct 2020) |
Request Required Commercial date (RCOD) |
(30th June 2021) except COVID-19 force majeure |
Civil Contract Award |
20th February 2019 |
Electro-mechanical Contract Award |
5th June 2020 |
Hydro-mechanical Contract Award |
26th July 2020 |
Transmission Line Award |
13th January 2021 |